Pushpam Infra Llp
Deedo IDDD-VEB7Of 7 registrations whose promised date has arrived, 3 kept it (43%). The rest ran a median 22 mo late.
Delivery record
7 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Sanskruti Row House P-IIDeregistered: Sanskruti Row House P-Ii | Not on record |
| Deregistered | 21 EnclaveDeregistered: 21 Enclave | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sanskruti Building AP52000011794 | Kashele | Certificate Signed | 31 Dec 2018 | 30 Jun 2022 | +42 mo |
| Swapna PushpaP52600011240 | Wangi | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Sanskruti B to E BuildingP52000013920 | Kashele | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Swapna PushpaP52600014141 | Wangi | Certificate Signed | 31 Dec 2019 | 30 Jun 2023 | +82 mo* |
| 21 EnclaveP52000035127 | Kashele | Certificate Signed | 31 May 2024 | 31 May 2024 | +29 mo* |
| Sanskruti Row House P-IIP52000035200 | Kashele | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +22 mo* |
| 21 EnclaveP52000045327 | Kashele | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| BalibaugP52000050292 | Kawir | Certificate Signed | 21 Mar 2025 | 21 Mar 2025 | On date |
| Balibaug RekreasiP52000077037 | Kawir | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Luxe-28P52000079519 | Kashele | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Pushpam Infra Llp, in questions
Does Pushpam Infra Llp finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 3 kept it (43%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pushpam Infra Llp registered with MahaRERA?
9 projects under 10 MahaRERA registrations; 4 completed on MahaRERA.
Does Pushpam Infra Llp have MahaRERA regulatory cases?
2 regulatory cases name its registrations.