Company or firm · first RERA registration 2017

Pushkar Homes Private Limited

Of 3 registrations whose promised date has arrived, 1 were never extended past it (33%). When extended, the date moved a median 41 mo — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay41 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Pushkar Homes Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Pushkar Govind and Narayan ApartmentP50500005009Nagpur (M Corp.)Certificate Signed31 Dec 201731 Dec 2018+12 mo
Pushkar Orchid Greens Phase IP50500006050Nagpur (Rural)Certificate Signed30 Jun 201830 Jun 2018On date
Pushkar SignatureP50500009067Nagpur (M Corp.)Certificate Signed31 Mar 201931 Dec 2024+69 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology