Company or firm · first RERA registration 2017
Pushkar Homes Private Limited
Of 3 registrations whose promised date has arrived, 1 were never extended past it (33%). When extended, the date moved a median 41 mo — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay41 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pushkar Govind and Narayan ApartmentP50500005009 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2017 | 31 Dec 2018 | +12 mo |
| Pushkar Orchid Greens Phase IP50500006050 | Nagpur (Rural) | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Pushkar SignatureP50500009067 | Nagpur (M Corp.) | Certificate Signed | 31 Mar 2019 | 31 Dec 2024 | +69 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology