Punir Gaurav Developers Pvt Ltd

Of 3 registrations whose promised date has arrived, 2 were never extended past it (67%).

Projects33 RERA registrations
Kept RERA date67%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Punir Gaurav Developers Pvt Ltd developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Punir Gaurav - ShriwardhanP51700001793PunirCertificate Signed30 Apr 201930 Apr 2019On date
Punir Gaurav Ph 1- ShriwardhanP51700003820PunirCertificate Signed30 Sep 202030 Sep 2020On date
Punir Gaurav - B WingP52000033098PunirCertificate Signed30 Apr 202430 Apr 2026+24 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology