Individual promoter · first RERA registration 2019

Pruthviraj Balkrishna Mhatre

Deedo IDDD-C3R9

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 47 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay47 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SwaroopP51700021625Navi Mumbai (M Corp.)Certificate Signed16 Nov 202216 Nov 2022+47 mo*
Rb-DelightP52000022002Vadghar (Ct)Certificate Signed16 Nov 202216 Nov 2022On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology