Company or firm · first RERA registration 2021
Prestige Estates Projects Limited
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Prestige Jasdan ClassicP51900031285 | Mumbai City | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Prestige Daffodils ChslP51800031980 | Andheri | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Prestige Garden TrailsPR1330002501223 | Mira Bhayandar (M Corp.) | Certificate Signed | 31 Oct 2030 | 28 Feb 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology