Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%).
Projects33 RERA registrations
Kept RERA date50%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PRAYAG CITY Phase IP52000004381 | Vihighar | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| PRAYAG MEADOWS PHASE - lP52000017065 | Vichumbe | Certificate Signed | 25 Dec 2022 | 25 Dec 2022 | On date |
| Prayag GharkulP52000022086 | Vihighar | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |