Company or firm · first RERA registration 2017

Prayag Builders & Devlopers

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%).

Projects33 RERA registrations
Kept RERA date50%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record

2 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
PRAYAG CITY Phase IP52000004381VihigharCertificate Signed31 Dec 201930 Dec 2021+24 mo
PRAYAG MEADOWS PHASE - lP52000017065VichumbeCertificate Signed25 Dec 202225 Dec 2022On date
Prayag GharkulP52000022086VihigharCertificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology