Individual promoter · first RERA registration 2017

Prakash Giridhar Amrutkar

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 56 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay56 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Amrut YogP51600009867Nashik (M Corp.)Certificate Signed16 Jul 201818 Feb 2023+55 mo
Amrut DarshanP51600012605Nashik (M Corp.)Completed16 Jan 201818 Sep 2022+56 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology