Company or firm · first RERA registration 2019
Pragati Developers
Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Saptashrungi SaharaP51600021736 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Saptashrungi VandanP51600027711 | Nashik (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Saptashrungi CharanP51600034782 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology