Prabhav Vijay Khawase

Deedo IDDD-TRV8

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredMahalaxmi PrideDeregistered: MAHALAXMI PRIDENot on record
DeregisteredMahalaxmi ResidencyDeregistered: MAHALAXMI RESIDENCYNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mahalaxmi ResidencyP50500024213Nagpur (M Corp.)Certificate Signed30 May 202230 May 2022+53 mo*
Mahalaxmi PrideP50500045753Nagpur (M Corp.)Certificate Signed31 Dec 202331 Dec 2023+34 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology