Pioneer Housing

Deedo IDDD-T9H5

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Senroofs Phase - IIP51800008478KurlaCertificate Signed31 Dec 201831 Dec 2018On date
Senroofs Phase - IIIP51800032087KurlaCertificate Signed31 Dec 202730 Apr 2028+4 mo
Senroofs Phase IV, Building No D1, Wing A Known As SolanaP51800055478NahurCertificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology