Company or firm · first RERA registration 2023

Pawshe Group Builders And Developers

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Pawshe Group Builders And Developers developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Pawshe PrideP51700051148KatemanevaliCertificate Signed30 Apr 202830 Aug 2028+4 mo
Pawshe ArcadePR1330002501686KatemanevaliCertificate Signed31 Dec 202830 Apr 2029+4 mo