Company or firm · first RERA registration 2019
Parklane Construction Llp
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects14 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Parklane UrbanjoyP52100019327 | Sus | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Parklane UrbanjoyP52100026272 | Sus | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Parklane UrbanjoyP52100080095 | Sus | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Parklane UrbanjoyPR1263032501780 | Sus | Certificate Signed | 31 May 2029 | 30 Sep 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology