Company or firm · first RERA registration 2019

Parklane Construction Llp

Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects14 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Parklane Construction Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 4 moved past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Parklane UrbanjoyP52100019327SusCertificate Signed30 Mar 202430 Mar 2024On date
Parklane UrbanjoyP52100026272SusCertificate Signed31 Dec 202731 Dec 2027On date
Parklane UrbanjoyP52100080095SusCertificate Signed31 Dec 202830 Apr 2029+4 mo
Parklane UrbanjoyPR1263032501780SusCertificate Signed31 May 202930 Sep 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology