Company or firm · first RERA registration 2017
Parakh Plexus Realty Ltd
Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed3as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PPRL Mera Ghar - Building L1P49900001386 | Jalgaon (M Corp.) | Completed | 31 Dec 2018 | — | On date |
| PPRL Mera Ghar - Building M1P49900001591 | Jalgaon (M Corp.) | Completed | 31 Dec 2018 | — | On date |
| PPRL Mera Ghar - Building E2P49900001778 | Jalgaon (M Corp.) | Completed | 31 Dec 2019 | — | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology