Company or firm · first RERA registration 2022

Paradiso Builders Private Limited

Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Paradiso Builders Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
DreamsvilleP51800046670BorivaliCertificate Signed31 May 202431 May 2024On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology