Company or firm · first RERA registration 2017

Paradigm Real Estates Llp

Deedo IDDD-EBHJ

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 52 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay52 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Casa PalazzoP51800008441BorivaliCertificate Signed31 Mar 201928 Feb 2022+91 mo*
NivanP51800011423AndheriCertificate Signed31 Oct 201831 Oct 2019+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology