Company or firm · first RERA registration 2017

Panch Tatva Realty

Deedo IDDD-12CT

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 64 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay64 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Tridhaatu PrarambhP51800012185KurlaCertificate Signed30 Jun 202131 Mar 2024+64 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology