Onyx Promoters Llp

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Gagan AvenciaP52100005102KharadiCertificate Signed30 Mar 202330 Sep 2025+43 mo*
Gagan AvenciaPR1261012500098KharadiCertificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology