Company or firm · first RERA registration 2017
Onyx Promoters Llp
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Gagan AvenciaRegulatory order: PROJECT NAME:GAGAN AVENCIA (Regulatory Case No.132 of 2024) dated 1 February 2024. | 1 Feb 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gagan AvenciaP52100005102 | Kharadi | Certificate Signed | 30 Mar 2023 | 30 Sep 2025 | +43 mo* |
| Gagan AvenciaPR1261012500098 | Kharadi | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology