Om Civil Constructions

Deedo IDDD-M2J8

Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 19 mo late.

Projects55 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay19 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rukhmini ComplexP52000020689Vadghar (Ct)Certificate Signed30 Jan 202230 Jan 2022On date
Ubha VitevariP52000022973Vadghar (Ct)Certificate Signed30 Oct 202230 Oct 2022On date
Jay Vitthal ComplexP52000024742Vadghar (Ct)Certificate Signed30 Jan 202330 Jan 2023On date
Hari VitthalP52000030397Vadghar (Ct)Certificate Signed31 Dec 202331 Dec 2023+34 mo*
Jay Vitthal Complex 1P52000078326DapoliCertificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology