Company or firm · first RERA registration 2019
Om Civil Constructions
Deedo IDDD-M2J8Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 19 mo late.
Projects55 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay19 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rukhmini ComplexP52000020689 | Vadghar (Ct) | Certificate Signed | 30 Jan 2022 | 30 Jan 2022 | On date |
| Ubha VitevariP52000022973 | Vadghar (Ct) | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Jay Vitthal ComplexP52000024742 | Vadghar (Ct) | Certificate Signed | 30 Jan 2023 | 30 Jan 2023 | On date |
| Hari VitthalP52000030397 | Vadghar (Ct) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +34 mo* |
| Jay Vitthal Complex 1P52000078326 | Dapoli | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology