Company or firm · first RERA registration 2017
Ocean Developers
Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
No registration has run past its RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ocean PearlP99000004132 | Palghar | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |