Nyati Builders Private Limited

Company or firm · 16 projects · 21 MahaRERA registrations

16Projects21 RERA registrations
0Completedas reported on MahaRERA project pages
87%Kept RERA date13 of 15 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 8 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nyati Evara IP52100000455Undri2017Certificate Signed30 Jun 201930 Jun 2019On date
Nyati Unitree IIP52100001629Pune City2017Certificate Signed31 Jan 202131 Jan 2021On date
NYATI ETHOS I - A1-PartP52100001879Undri2017Certificate Signed31 Jul 202231 Jul 2022On date
Nyati Ethos I - B3P52100002024Undri2017Certificate Signed31 Jul 202231 Jul 2022On date
Nyati Enchante IP52100015299Haveli2018Certificate Signed30 Sep 202030 Sep 2020On date
Nyati EricaP52100017027Undri2018Certificate Signed30 Dec 202130 Dec 2021On date
Nyati EnchanteP52100018860Vadgaonsheri2018Certificate Signed30 Mar 202130 Mar 2021On date
Nyati EnchanteP52100020656Vadgaonsheri2019Certificate Signed30 Mar 202130 Mar 2021On date
Nyati Evara IIP52100021346Undri2019Certificate Signed30 Sep 202030 Sep 2020On date
Nyati ExuberanceP52100027031Undri2020Certificate Signed30 Sep 202430 Sep 2025+12 months
Nyati ExuberanceP52100034932Undri2022Certificate Signed30 Jun 202430 Jun 2025+12 months
Nyati ExuberanceP52100048720Undri2023Certificate Signed31 Mar 202531 Mar 2025On date
Nyati Defence EnclaveP52100048851Mohammadwadi2023Certificate Signed31 Dec 202431 Dec 2024On date
Nyati Defence EnclaveP52100048915Mohammadwadi2023Certificate Signed31 Dec 202431 Dec 2024On date
Nyati Defence EnclaveP52100050321Mohammadwadi2023Certificate Signed31 Dec 202431 Dec 2024On date
Nyati Emerald IP52100051235Baner2023Certificate Signed31 May 202730 Sep 2027+4 months
Nyati Exuberance IVP52100053576Undri2023Certificate Signed31 Mar 202731 Jul 2027+4 months
Nyati Emerald IIP52100054857Baner2024Certificate Signed28 Feb 202728 Jun 2027+4 months
Nyati Emerald IIIP52100055066Baner2024Certificate Signed31 Aug 202831 Dec 2028+4 months
Nyati EvoqueP52100056152Vadgaonsheri2024Certificate Signed31 Dec 202730 Apr 2028+4 months
Nyati ElenorP52100078873Bibwewadi Munjeri2025Certificate Signed30 Oct 202928 Feb 2030+4 months
Show all 21 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nyati Evara IOn date
  • Nyati Unitree IIOn date
  • NYATI ETHOS I - A1-PartOn date
  • Nyati Ethos I - B3On date
  • Nyati Enchante IOn date
  • Nyati EricaOn date
  • Nyati EnchanteOn date
  • Nyati EnchanteOn date
  • Nyati Evara IIOn date
  • Nyati Exuberance+12 mo
Show all 21 registrations
  • Nyati Exuberance+12 mo
  • Nyati ExuberanceOn date
  • Nyati Defence EnclaveOn date
  • Nyati Defence EnclaveOn date
  • Nyati Defence EnclaveOn date
  • Nyati Emerald I+4 mo
  • Nyati Exuberance IV+4 mo
  • Nyati Emerald II+4 mo
  • Nyati Emerald III+4 mo
  • Nyati Evoque+4 mo
  • Nyati Elenor+4 mo

Track record notes

  • 13 of 15 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Nyati Exuberance (P52100027031).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology