Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kanchan VatikaP99000026327PalgharCertificate Signed4 Nov 20234 Nov 2023On date
Shree SaketP99000049384PalgharCertificate Signed25 Dec 202525 Dec 2025On date
Kanchan Business Hub And Kanchan HeightsP99000076735PalgharCertificate Signed30 Apr 203030 Aug 2030+4 mo