Company or firm · first RERA registration 2022
Nivasa Associates
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects13 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nivasa EnchanteP52100034898 | Lohgaon | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Nivasa EnchanteP52100053779 | Lohgaon | Certificate Signed | 31 Aug 2026 | 31 Dec 2026 | +4 mo |
| Nivasa EnchanteP52100079778 | Lohgaon | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology