Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
Flats sold, all time3registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Nexus Kinaara B CP52100031120ChikhaliCertificate Signed30 Aug 202429 Aug 2025+12 mo
Nexus Kinaara DP52100033605ChikhaliCertificate Signed31 Dec 202430 Dec 2025+12 mo
Nexus Kinaara AP52100051339ChikhaliCertificate Signed30 Apr 202830 Apr 2028On date