Company or firm · first RERA registration 2019
New Unicon Infraventures Llp
Deedo IDDD-0MNYOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 3 mo late — shorter than Maharashtra's 4 mo.
Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay3 mowhen late · Maharashtra: 4 mo
Flats sold, all time35registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| One Place BanerP52100019578 | Baner | Certificate Signed | 30 Dec 2024 | 13 Mar 2025 | +3 mo |
| One Place BanerP52100019584 | Baner | Certificate Signed | 30 Dec 2024 | 13 Mar 2025 | +3 mo |
| One Place Baner Phase IIIP52100034262 | Baner | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology