Company or firm · first RERA registration 2021

New Manikraj Developers

Deedo IDDD-G438

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay30 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mandai ComplexP52100027785Shirur GraminCertificate Signed1 Apr 20241 Apr 2024+30 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology