Neelkanth Enterprises

Deedo IDDD-C412

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 10 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Neelkanth SparkleP51700005915Navi Mumbai (M Corp.)Certificate Signed30 Jun 201830 Jun 2018On date
Cloud 9P52000056475PaleCertificate Signed31 Dec 202531 Dec 2025+10 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology