Company or firm · first RERA registration 2017

Nasa Construction Pvt.Ltd

Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Nasa Construction Pvt.Ltd developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Sai Sagar AP51600004324NashikCertificate Signed1 Jan 20211 Jan 2021On date