Naiknavarehousingdevelopementspvtltd
Deedo IDDD-QNV6Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Dwarka Project3Regulatory order: PROJECT NAME:DWARKA PROJECT3 (Regulatory Case No. 170 of 2024) dated 13 March 2024. | 13 Mar 2024 |
| Regulatory order | Dwarka Project2Regulatory order: PROJECT NAME:DWARKA PROJECT2 (Regulatory Case No. 169 of 2024) dated 13 March 2024. | 13 Mar 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dwarka Project3P52100000163 | Mahalunge | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | +4 mo* |
| Dwarka Project 1P52100000164 | Mahalunge | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Dwarka Project2P52100000168 | Mahalunge | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology