Company or firm · first RERA registration 2017

Naiknavarehousingdevelopementspvtltd

Deedo IDDD-QNV6

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dwarka Project3P52100000163MahalungeCertificate Signed30 Jun 202630 Jun 2026+4 mo*
Dwarka Project 1P52100000164MahalungeCertificate Signed31 Dec 201831 Dec 2018On date
Dwarka Project2P52100000168MahalungeCertificate Signed31 Dec 202731 Dec 2027On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology