Company or firm · first RERA registration 2021
N V Construction
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Mangal Narayan ResidencyP51700030047 | Kalyandombivali (M Corp.) | Certificate Signed | 31 Dec 2023 | 31 Dec 2025 | +34 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
