Mukesh Rajmal Parekh
Deedo IDDD-QCK1None of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Oshia ResidencyPR1180002600618 | Vileparle | Certificate Signed | 30 Mar 2029 | 30 Jul 2029 | +4 mo |
Mukesh Rajmal Parekh, in questions
Does Mukesh Rajmal Parekh finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Mukesh Rajmal Parekh registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Mukesh Rajmal Parekh have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.