Company or firm · first RERA registration 2021

Model Developers And Gengaje Associates

Deedo IDDD-799N

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Samarth SadanP52700029437SataraCertificate Signed31 Mar 202431 Mar 2024On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology