Company or firm · first RERA registration 2017

Mittal Vastushilp Llp

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 28 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay28 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sun AuraP52100000302Wadgaon BkCertificate Signed31 Dec 201831 Dec 2018On date
Sun VistaP52100030202Wadgaon BkCertificate Signed30 Jun 202430 Jun 2024+28 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology