Company or firm · first RERA registration 2017
Milan Interbuilt Private Limited
Of 3 registrations whose promised date has arrived, 1 were never extended past it (33%).
Projects33 RERA registrations
Kept RERA date33%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Meghdoot ResidencyP51800003357 | Andheri | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Nazareth NiketanP51800008647 | Andheri | Certificate Signed | 31 Mar 2018 | 31 Mar 2019 | +12 mo |
| Alpine BuildingP51800018586 | Andheri | Certificate Signed | 30 Jun 2021 | 31 Mar 2023 | +21 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology