Company or firm · first RERA registration 2024
Mextech Property Developers LLP
None of 4 registrations has reached its promised completion date yet.
Projects44 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
3 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Miraya DivineComplaint CC12600483 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Miraya DivineP51700055585 | Thane (M Corp.) | Active | 15 Dec 2029 | — | On date |
| Miraya Business HubP51700055878 | Thane (M Corp.) | Certificate Signed | 15 Dec 2028 | 15 Apr 2029 | +4 mo |
| Miraya Trinity - EternityP51700080732 | Thane (M Corp.) | Certificate Signed | 15 Dec 2029 | 15 Apr 2030 | +4 mo |
| Miraya Trinity - SerenityP51700080866 | Thane (M Corp.) | Certificate Signed | 15 Dec 2029 | 15 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology