Mayuri Landmarksllp
Deedo IDDD-3655Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 26 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay26 mowhen late · Maharashtra: 4 mo
Flats sold, all time91registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mayuri InfinityP52100015703 | Undri | Certificate Signed | 30 Apr 2021 | 30 Apr 2025 | +48 mo |
| Mayuri AdhinathpuramP52100049330 | Undri | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology