Company or firm · first RERA registration 2017
Mantra Erectors And Builders Llp
Deedo IDDD-QP4POf 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Projects35 RERA registrations
Kept RERA date40%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mantra 24westP52100001260 | Gahunje | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
| Phase 1 Of Mantra 24 WestP52100001377 | Gahunje | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | On date |
| Mantra 24westP52100001660 | Gahunje | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
| Mantra 24westP52100002639 | Gahunje | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
| Mantra 24 West Phase 7P52100026074 | Gahunje | Certificate Signed | 28 Feb 2023 | 28 Feb 2023 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology