Company or firm · first RERA registration 2017
Mantra 29 Gold Cost Developers Llp
Deedo IDDD-8X02Of 7 registrations whose promised date has arrived, 4 kept it (57%). The rest ran a median 20 mo late.
Projects67 RERA registrations
Kept RERA date57%Maharashtra: 73%
Median delay20 mowhen late
Flats sold, all time58registered sale deeds
Regulatory cases0none on record
3 registrations of 7 ran past the RERA date
Months late against the original RERA promise, per registration
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| 29 Gold Coast Phase 1P52100002674 | Dhanori | Certificate Signed | 19 Mar 2021 | 19 Sep 2022 | +18 mo |
| 29 Gold Coast Phase 2P52100016777 | Dhanori | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| 29 Gold Coast Phase 3P52100017100 | Dhanori | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| 29 Gold CoastP52100023097 | Dhanori | Certificate Signed | 28 Nov 2023 | 28 Nov 2023 | On date |
| 29 Gold CoastP52100023345 | Dhanori | Certificate Signed | 28 Nov 2023 | 28 Nov 2023 | On date |
| 29 Gold Coast Phase 6P52100029378 | Dhanori | Certificate Signed | 31 Dec 2024 | 31 Dec 2025 | +22 mo* |
| 29 Gold Coast Phase 7P52100045500 | Haveli | Certificate Signed | 16 Feb 2025 | 16 Feb 2025 | +20 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology