Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects89 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Godrej BoulevardP52100024616Manjari KhCertificate Signed30 Sep 202530 Sep 2025On date
Godrej Park SpringsP52100026739Manjari KhCertificate Signed30 Mar 202530 Sep 2029+54 mo
Godrej ParkridgeP52100028310Manjari KhCertificate Signed30 Sep 202530 Sep 2025On date
Godrej Sky GreensP52100032428Manjari KhCertificate Signed31 Dec 202631 Dec 2026On date
Godrej Sky GreensP52100032794Manjari KhCertificate Signed31 Dec 202631 Dec 2026On date
Godrej Urban RetreatP52100050128Manjari KhCertificate Signed11 Oct 202711 Oct 2027On date
Godrej River CrestP52100077127Manjari KhCertificate Signed15 Jun 203015 Jun 2030On date
Sarita NiketanP52100079924Manjari KhCertificate Signed15 Dec 202815 Apr 2029+4 mo
Godrej IvaraPR1260002502426WagholiCertificate Signed16 Aug 203216 Dec 2032+4 mo