Maharashtra Housing And Area Development Authority

Deedo IDDD-QCBA

Of 10 registrations whose promised date has arrived, 4 kept it (40%). The rest ran a median 60 mo late.

Projects1111 RERA registrations
Kept RERA date40%Maharashtra: 73%
Median delay60 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

7 registrations of 11 ran past the RERA date

Months late against the original RERA promise, per registration

11 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Plot No 3 Charkop Sector 8P51800000017BorivaliCertificate Signed31 Dec 201830 Oct 2020+22 mo
Plot No.2P51800000019BorivaliCertificate Signed30 Dec 201830 Dec 2018On date
Constn of 219 Ts and 172 MIG Ts on CTS No 128 A 12 Pt at Mahaveer nagar Kandivali W MumbaiP51800000040BorivaliCertificate Signed31 Dec 201930 Dec 2021+24 mo
Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum TurnkeyP51800000041AndheriCertificate Signed30 Jun 201830 Oct 2020+100 mo*
Construction of 86 Tenements out of 430 MIG tenements of old Magathane village BorivaliP51800000063BorivaliCertificate Signed13 Dec 201813 Dec 2018On date
64 LIG, 80 MIG, 16HIG and 20 Shops at Sr. No. 491, Res. No. 23 Part, Vengurla, Dist. SindhudurgP51800002323AndheriCertificate Signed31 May 201831 May 2018On date
Plotted Development Scheme at Sindhudurhnagari, Oras, Tal- Kudal, Dist- SindhudurgP51800008115AndheriCertificate Signed31 Dec 201731 Dec 2017+106 mo*
Const Of 586 Ews 234 Mig Tenaments On Land Bearing Cts No 1 C 1 1 Borivali West Mumbai 67P51800008549BorivaliCertificate Signed31 Dec 201731 Dec 2017On date
Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThaneP51700016820SherdonCertificate Signed25 Mar 202224 Mar 2027+60 mo
Survey No 162 Village Khoni Tal KalyanP51700016831KhoniCertificate Signed9 Jan 20227 Jan 2028+72 mo
Proposed Redevelopment of existing Transit Camp at Sion, Construction of 91 EWS T/s. 285 Transit T/s +19 shops, 31 LIG T/s, 56 MIG T/s, on land bearing CS. No. 4(Pt.) salt pan Dn. F/N ward at Sion PH -V, MumbaiPR1170002600192SionCertificate Signed31 Dec 203030 Apr 2031+4 mo
Show all 11 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology