Mahalaxmi Buildcon

Deedo IDDD-7ZKY

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mahalaxmi Nagar 7P50500017689KothewadaCertificate Signed28 Aug 202228 Aug 2022On date
Mahalaxmi Nagar 12P50500025462JamthaCertificate Signed30 Nov 202330 Nov 2023On date
Mahalaxmi Nagar - 18P50500029585JamthaCertificate Signed30 Jun 202430 Jun 2024On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology