Magnum Developers
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AuroraP52100030790 | Wagholi | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| AuroraP52100047622 | Wagholi | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology