Company or firm · first RERA registration 2019
Madhav Infra
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 50 mo — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay50 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Aadhar NagariRegulatory order: PROJECT NAME: AADHAR NAGARI (Regulatory Case No. 287 OF 2024) dated 09 Aug 2024. | 9 Aug 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aadhar NagariP50500023088 | Hingna | Certificate Signed | 28 Oct 2023 | 31 Dec 2027 | +50 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology