Company or firm · first RERA registration 2017
Lucina Land Development Limited
Deedo IDDD-TR9JNone of 5 registrations has reached its promised completion date yet.
Projects15 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases6no insolvency
2 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
Show all 30 casesShow fewer
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Indiabulls ParkP52000000475 | Kon | Certificate Signed | 30 Dec 2030 | 30 Dec 2030 | On date |
| Indiabulls ParkP52000000488 | Kon | Certificate Signed | 30 Apr 2030 | 30 Aug 2030 | +4 mo |
| Indiabulls ParkP52000000709 | Kon | Certificate Signed | 30 Mar 2029 | 30 Mar 2029 | On date |
| Indiabulls ParkP52000000835 | Kon | Certificate Signed | 30 Jun 2029 | 30 Jun 2029 | On date |
| Indiabulls ParkP52000025902 | Kon | Certificate Signed | 30 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology