Lucina Land Development Limited

Deedo IDDD-TR9J

None of 5 registrations has reached its promised completion date yet.

Projects15 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases6no insolvency

2 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 5 (Regulatory Case No. 220 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 5 (Regulatory Case No. 220 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 5 (Regulatory Case No. 220 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 5 (Regulatory Case No. 220 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 5 (Regulatory Case No. 220 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 4 (Regulatory Case No. 219 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 4 (Regulatory Case No. 219 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 4 (Regulatory Case No. 219 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 4 (Regulatory Case No. 219 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 4 (Regulatory Case No. 219 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 3 (Regulatory Case No. 218 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 3 (Regulatory Case No. 218 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 3 (Regulatory Case No. 218 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 3 (Regulatory Case No. 218 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 3 (Regulatory Case No. 218 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 2 (Regulatory Case No. 217 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 2 (Regulatory Case No. 217 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 2 (Regulatory Case No. 217 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 2 (Regulatory Case No. 217 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 2 (Regulatory Case No. 217 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 1 (Regulatory Case No. 216 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 1 (Regulatory Case No. 216 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 1 (Regulatory Case No. 216 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 1 (Regulatory Case No. 216 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS PARK 1 (Regulatory Case No. 216 OF 2024) dated 31 May 2024.31 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS SAVROLI - 3 (Regulatory Case No. 215 OF 2024) dated 31 May 2024.30 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS SAVROLI - 3 (Regulatory Case No. 215 OF 2024) dated 31 May 2024.30 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS SAVROLI - 3 (Regulatory Case No. 215 OF 2024) dated 31 May 2024.30 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS SAVROLI - 3 (Regulatory Case No. 215 OF 2024) dated 31 May 2024.30 May 2024
Regulatory orderIndiabulls ParkRegulatory order: PROJECT NAME:INDIABULLS SAVROLI - 3 (Regulatory Case No. 215 OF 2024) dated 31 May 2024.30 May 2024
Show all 30 casesShow fewer

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Indiabulls ParkP52000000475KonCertificate Signed30 Dec 203030 Dec 2030On date
Indiabulls ParkP52000000488KonCertificate Signed30 Apr 203030 Aug 2030+4 mo
Indiabulls ParkP52000000709KonCertificate Signed30 Mar 202930 Mar 2029On date
Indiabulls ParkP52000000835KonCertificate Signed30 Jun 202930 Jun 2029On date
Indiabulls ParkP52000025902KonCertificate Signed30 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology