Lok Nagari Developer
Deedo IDDD-5QFEOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay21 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Lok Nagari DeveloperP51700006820 | Ambarnath (R) | Certificate Signed | 30 Jun 2021 | 29 Dec 2022 | +18 mo |
| Lok Nagari DeveloperP51700010802 | Ambarnath (R) | Certificate Signed | 30 Dec 2019 | 29 Dec 2021 | +24 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology