Skip to content
Company or firm · first RERA registration 2017

Lodha Builders And Developers

Deedo IDDD-YHP6

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dreams HeightsP99000005381Vasai Virar City (M Corp)Certificate Signed30 Mar 202330 Sep 2025+43 mo*
Dreams HeightsP99000009825Vasai Virar City (M Corp)Certificate Signed30 Sep 202630 Sep 2026+1 mo*
Dreams Heights Building No II C WingP99000048499Vasai Virar City (M Corp)Certificate Signed31 Mar 202931 Jul 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology