Company or firm · first RERA registration 2017
Lodha Builders And Developers
Deedo IDDD-YHP6Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dreams HeightsP99000005381 | Vasai Virar City (M Corp) | Certificate Signed | 30 Mar 2023 | 30 Sep 2025 | +43 mo* |
| Dreams HeightsP99000009825 | Vasai Virar City (M Corp) | Certificate Signed | 30 Sep 2026 | 30 Sep 2026 | +1 mo* |
| Dreams Heights Building No II C WingP99000048499 | Vasai Virar City (M Corp) | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology