Ljmk Developers Llp

Deedo IDDD-W7QB

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay30 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Royal ArcadeP52100019636Kondhwa KhurdCertificate Signed30 Dec 202431 Dec 2027+36 mo
Royal ArcadeP52100019743Kondhwa KhurdCertificate Signed30 Dec 202531 Dec 2027+24 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology