Company or firm · first RERA registration 2020
Lisha Construction
Deedo IDDD-5A7NOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 40 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay40 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Guruwarya Chikane Guruji ResidencyP52800026146 | Khed (M Cl) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | +40 mo* |
| Lisha ResidencyP52800027669 | Khed (M Cl) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
