Company or firm · first RERA registration 2018

Laxmi Developers

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%).

Projects22 RERA registrations
Kept RERA date50%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Laxmi Developers developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Om RamchandraP51700017328KalyanCertificate Signed30 Nov 202030 Nov 2020On date
Omkar SwarupaP51700022529TitwalaNot on record30 Jun 202430 Jun 2025+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology