Laxmi Builders
Deedo IDDD-18CHOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 34 mo late.
Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Lambodar AnnexDeregistered: Lambodar Annex | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mangalmurti ResidencyP51600030199 | Nashik (M Corp.) | Certificate Signed | 31 Jul 2023 | 31 Jul 2023 | On date |
| Parvati AnnexP51600030650 | Nashik (M Corp.) | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | On date |
| Lambodar AnnexP51600032830 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +34 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology