Laxmi Builders

Deedo IDDD-18CH

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 34 mo late.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredLambodar AnnexDeregistered: Lambodar AnnexNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mangalmurti ResidencyP51600030199Nashik (M Corp.)Certificate Signed31 Jul 202331 Jul 2023On date
Parvati AnnexP51600030650Nashik (M Corp.)Certificate Signed30 Apr 202430 Apr 2024On date
Lambodar AnnexP51600032830Nashik (M Corp.)Certificate Signed31 Dec 202331 Dec 2023+34 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology