Landmark Infra

Deedo IDDD-WCRD

Of 4 registrations whose promised date has arrived, 4 kept it (100%).

Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shiv NakshatraP51600006926Jail RoadCertificate Signed31 Oct 201931 Oct 2019On date
Shiv EnclaveP51600027426Nashik (M Corp.)Certificate Signed1 Feb 20231 Feb 2023On date
Shiv HarmonyP51600030095Nashik RoadCertificate Signed31 Oct 202331 Oct 2023On date
Shiv OrchidP51600049498Nashik RoadCertificate Signed31 Dec 202431 Dec 2024On date
Shiv EmpireP51600055916Nashik (M Corp.)Certificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology