Landmark Infra
Deedo IDDD-WCRDOf 4 registrations whose promised date has arrived, 4 kept it (100%).
Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shiv NakshatraP51600006926 | Jail Road | Certificate Signed | 31 Oct 2019 | 31 Oct 2019 | On date |
| Shiv EnclaveP51600027426 | Nashik (M Corp.) | Certificate Signed | 1 Feb 2023 | 1 Feb 2023 | On date |
| Shiv HarmonyP51600030095 | Nashik Road | Certificate Signed | 31 Oct 2023 | 31 Oct 2023 | On date |
| Shiv OrchidP51600049498 | Nashik Road | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Shiv EmpireP51600055916 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology